Some photos of work at Duffield over the last couple of weeks:
Removal of decayed wooden sleepers, leveling the track bed for the new mainline and starting to layout the concrete sleepers. Hopefully we might get some rail down next week.
There is also a photo showing access to out platform form Network Rail, Matlock Train in NR platform.
We have decided to postpone the opening until 8th April 2011. We still have to finish by the end of September 2010 but it will give us time to get everything looking good for the opening. Also we will be able to make much more use of the visiting steam engine and probably keep it untill early June 2011.
We will run some trains for members and shareholders next October.
Best wishes,
John H-T.
|