Another case of Party Manifesto being published before doing a reality check. The upgrade timetable required twice the number of workers than Network Rail employ, they can't be in two places at once. Rebuilding railways that are on track-beds 170 years old will throw up unexpected problems, the re-boring of Farnworth tunnel being a good example. These problems all add to additional time and cost.