I have more photos to post Most of the track work at Duffield is now complete. Both crossovers for the loop are installed and there are now just 7 pannels of track to lay. Quite a few of the sleepers are down and the rail is due to be delivered at the beginning of the year.
The weather is slowing us down a bit. We have not been able to get a loco down to Duffield this week because of the air brakes freezing. It hasn't really gone above freezing at Wirksworth for about 5 days! We have managed to run all our Santa Trains as planned.
Frozen Ballast is also slowing work.
Photos as ever are on the Web site in the "today" section:
http://www.evra.org.uk/index2.htm
There are some from yesterday.
Will post some of mine soon.
Best wishes,
John H-T.